In 2025, Xi’an Brictec will launch its second major engineering project in Iraq — the KTB sintered brick production line. The project plans to build three modern tunnel kiln sintered brick production lines, to be advanced in three phases. After the completion of Phase I and Phase II, the total daily output is expected to reach 900 tons, mainly producing clay sintered bricks with the specification of 240*115*75mm, 400*200*200mm, 200*400*200mm. This project not only consolidates Xi’an Brictec’s leading position in the Middle Eastern market but also provides strong technical support for the upgrading and transformation of Iraq’s building materials industry.
![]()
Latest construction progress as of August 2025:
Third batch of goods arrived at the site
![]()
Tunnel kiln masonry construction
![]()
250T kiln wall construction at the discharge end
![]()
650T kiln foundation pit construction
![]()
Retaining wall construction for Chenhua warehouse
![]()
V-shaped foundation construction for Chenhua warehouse commenced
Copyright Notice:
All images are sourced from Brictec Iraq project site photography. Unauthorized use will be pursued for legal liability.
Edited by: JF & Lou